Highest free standing Wind Measurement Mast in Nothern Germany
Most comprehensive project of Ge:Net so far
Ge:Net has again successfully installed a free standing wind measurement mast near
the German north sea coast.
In summer 2017 our customer approached us with a request for an offer about a free
standing mast. Nobody imagined that this would result in the most comprehensive
project of the company so far.
Already in August we received the order with challenging aims:
- The mast should be erected until end of 2017.
- The foundation was already built and did not fulfill our requirements.
We accepted the challenge and started by developing a transition piece for the old
foundation and the new mast with 110m height. From the very beginning our client
made perfectly clear that only the highest quality standards would be accepted. All
planning and production would be closely monitored by them.
With delight we accomplished these tasks and fulfilled all quality requirements.
In October it got exciting: Though we were all working under high pressure the
erection in 2017 seemed not possible. To fulfill our customer’s request we all
worked even harder and the delivery of the first part of the mast in calendar week
49 was made possible.
Start of December the crane for the erection was ordered, the mast was assembled in
two large sections on the ground and on Friday the 15th of December 2017 the moment
was there: The mast was successfully erected.